Our Prieb Homes Warranty and Procedures Manual includes a time line of the building process that shows all the stages of construction. We thought it might make an easy, "at a glance" way to see how our construction is proceeding to include it here along with checkmarks indicating which ones are completed.
All items 100% as of Wednesday, March 12. Just a little over 7 months after the first item on the checklist.
X
I. Build Job Meeting (8/10)
X
II. Foundation Stage
X
Stake property
X
Dig foundation
X
Pour foundation
X
Set steel I-beams
X
waterproof basement / set drain tile
X
Set 1/2 stub for bath
X
Pour floor in basement
X
Backfill around foundation
X
III. Framing stage
X
Rough-in the house and complete sub-floors
X
Install siding
X
Install roof
X
Install windows
X
Install doors
X
Install garage door
X
IV. Interior Stage
X
Install fireplace
X
Install plumbing (pipe work)
X
Install duct work for furnace / air conditioning
X
Install electrical wiring
X
Install wiring for phone and cable outlets
X
Furdown heating / air conditioning ductwork
X
Install insulation
X
Install sheetrock
X
Order cabinets
X
Spray textured ceilings
X
V. Finish Stage
X
Install sump pump
X
Install wood flooring
X
Deliver and install interior doors
X
Deliver and set cabinets
X
Stain cabinets and fireplace trim
X
Measure counter tops
X
Install wood trim
X
Paint interior
X
Set counter tops in place
X
Install ceramic tile
X
Install vinyl flooring
X
Install cabinet hardware
X
Install light fixtures
X
Install faucets
X
Install and hook up furnace
X
Install and hook up A/C
X
Install and hook up water heater
X
Pour sidewalks
X
Pour driveway
X
Pour patio
X
Install shower door - mirrors
X
Install phone/cable outlets and plates
X
Preliminary finish on hardwood floor
X
Install hardware on doors
X
Install carpet
X
Do final finish on hardwood floors
X
Scrape windows
X
VI. Exterior Finish
X
Paint exterior
X
Do final grade
X
Lay sod (3/12)
X
Install guttering
X
Schedule final inspection
X
VII. Homeowner Orientation